This report is comprised of 3
sections as summarized below:
I. GRSC: concerns
and its status
Findings raise serious doubts regarding the
effectiveness of the GRSC. First, current status of the GRSC
process and the power and gender imbalance in its composition
should be noted. The commencement of GRSC's operation has
been delayed for nearly 2 months due the fact that 2 of its
members have not yet been selected. Furthermore, the only
meeting held so far was attended by only two member of the
GRSC. Information dissemination to local communities is clearly
insufficient and inadequate; none of the villagers I have
met were informed of the GRSC. In addition, the fact that
necessary information has not been provided to the ADB Management
by the Government of Pakistan (GoP) suggests inadequacy of
coordination between the ADB staff and GoP.
All of the members of the GRSC selected so far,
including the Representatives of People affected, are male,
powerful, and affluent figures of the society. It is important
to note that the selection procedures for the Representative
of People Affected were ignored, and an appointment was made
on the discretion of the local official. According to the
Requester, both representatives are prominent landlords and
are known for their alliances with the governmental officials.
In fact, one of the representatives has been the opponent
of the affectees' campaign.
Secondly, the confidence of local communities
in the GRSC, which is the prerequisite for any satisfactory
resolution to the disputes, is completely absent. When we
provided the villagers with the list of the GRSC members and
selection procedures of the Representatives of People Affected,
all villagers expressed strong distrust in the members of
the GRSC. In fact, some villagers have displayed outright
hostility against WAPDA and governmental officials based on
their past experiences and disappointments. Moreover, all
of the villagers rejected the legitimacy of the selection
procedures for the Representatives of People Affected, and
accurately speculated that the representatives appointed by
the Government would be affluent allies of the government.
In addition, they noted that two people could not possibly
represent the various and vast concerns of the communities.
Villagers were in unanimous agreement that the outcome of
the GRSC will not be positive or meaningful without a greater
presence of marginalized affectees in the GRSC, and that only
direct representation by the affectees was appropriate and
legitimate.
In contrast, staff of the ADB Resident Missions
believed that the GRSC is legitimate and adequate despite
the above concerns I have delivered to them. They did not
seem to understand the concerns of the Requesters and local
communities, and it is highly questionable if they have even
read the relevant documents, such as: Second Supplement to
the Inspection Claim, and Roster member's comment on the Recommendations
of the Board Inspection Committee. Furthermore, the staff
blamed the local NGOs for their disengagement in the GRSC;
however, it should be noted that no response has been made
by the ADB to the Requester's demand in the Second Supplement
that the GRSC, which states:
The Requesters would like to present the following demands
in the context of any insistence for negotiation and dialogue
in the future…The GRSC should be redesigned in the light of
the principles and guidelines provided by the World Commission
on Dams Final Report. Most importantly, the project affectees
should have fifty percent of the membership in the GRSC through
direct nomination of their legitimate representative forums…
Under such circumstances, the gap between the GRSC and the
local communities is not expected to be filled.
Moreover, I have heard complaints from every
villager regarding the corruption of the governmental officials
in delivery of compensations or remedies. It should be noted
that monitoring procedures of the GRSC told by the staff at
the Resident mission, as well as the ADB's current anti-corruption
measures, are inappropriate, and the recommendations of the
GRSC are not even legally binding.
II. Design failures
of the CRBIP, subsequent damages,
and other environmental and social impacts of CRBIP
It should be highlighted that the fundamental
design flaws seem to stem from careless disturbances with
the natural hydrology-failure to manage two different water
flows, the hill torrent from West to East, and main canal
from North to South. Combining several natural flood streams
per Flood Carrier Channel (FCC) has strengthened the destructive
force of the hill torrent, while the ill-designed cross-drainage
structures do not allow floodwater to cross the main canal,
resulting in extensive flooding in the area before the structures.
It should be noted that the study conducted
by Japan International Cooperation Association (JICA) for
the same hill torrents are different from the feasibility
study of the CRBIP regarding the figures of maximum discharges
of floodwater, etc. Furthermore, conclusion of JICA's study
recommends not to engineer intervention of flood hydrology
or disturb the watercourses.
According to the Requester, if local traditional
knowledge has been consulted and incorporated into the project,
such as use of existing natural floodwater channels and incorporation
of traditional hill torrent irrigation, obvious design flaws
and subsequent damages would have been prevented, and the
amount of land acquisition and project costs reduced. Instead,
the ADB documents suggest that the project design was based
mainly on economic and budgetary concerns, and without proper
consultations of the local communities or adequate environmental
assessment.
Furthermore, some obvious and grave design failures
seem to be caused by a simple lack of integrity or extreme
carelessness. Based on the interview with the Acting Chief
Engineer of WAPDA, it could be concluded that the shifting
of Indus River to the east since the 70's, has not been considered
in the project design. Therefore, the FCCs and distribution
canals (distributaries) do not reach their ultimate drainage
point, Indus River; instead, they terminate at the riverine
belt, which was the active bed of the Indus River when the
feasibility study was initially prepared in the 70's. As an
obvious consequence, the riverine belt has been extensively
flooded. It is difficult to imagine how such unequivocal and
fundamental design flaw based on the obsolete feasibility
study and topography passed the ADB's approval in 1991, and
has been ignored for more than a decade. The same is true
for the insufficient number of bridges over FCCs, inadequacy
and erosion of embankments, and distributaries that are too
deep to channel water to minor distributaries.
I have witnessed the extremely costly social
and environmental consequences of such budgetary restrictions
and alleged policy violation of the ADB. They include: extensive
flooding of the west side of the main canal and riverine belt;
destruction of villages and agricultural land, and production
of water-borne diseases due to flooding and breaching of the
distributaries; inevitable impoverishment of people due to
the lack of appropriate compensation and a resettlement plan;
risk of life caused by flooding and conflicts between ethnic
groups; water logging; restriction on villagers' mobility
and access to facilities; widened disparity between rich and
poor; and environmental destruction, such as deforestation,
land erosion, etc. Such situation especially disadvantages
women and marginalizes groups.
III. CRBIP-III induced
vulnerabilities
and some demands of the
local communities
Of the 7 villages I visited, I observed the
urgency of the vast and various project-induced vulnerabilities
that the local communities face and substantial burden imposed
on the communities that are already deprived of resources.
For example the village of Sokkar, population of 10,000, located
on the west side of the main canal, faces the danger of drowning
in floodwater in the flood protection embankment surrounding
the village. In fact, the embankment was almost breached by
the three flood streams that meet near the village last year.
Affectees of Morjhangi Village at the riverine belt mourned
that the entire village would submerge in free-flowing canal
water if the distributary is operated for few more days. A
villager of Lashari commented that they have became poorer
due to recurrent damage to crops. Women of the Kandi Walla
village are now forced to travel 5 to 6 km to obtain drinking
water due to failure of the drinking water scheme of the CRBIP.
It is important to note that their experiences
and demands are different depending on each situation of the
communities. Furthermore, accurate or exact figures of the
damages are not available regarding the extent of the land
acquired for the project, damages, etc. Such circumstances
illustrate the need for independent and comprehensive investigation
in full consultation with the communities in order to understand
the extent and nature of the project-induced vulnerabilities,
and to explore the possible solutions that are effective and
suitable for each community. Moreover, it is crucial to remember
that although most of the affectees demand land for land,
there is no resettlement plan. Mr. Gadi believes that the
resettlement guidelines and land acquisition guidelines required
for the National Drainage Programme (NDP) are applicable in
the CRBIP because of supplementary financing through directing
NDP loan proceeds to the CRBIP .
|